Investment Case

A Clear strategy for Growth

IRC is a vertically integrated
producer of industrial
commodities, notably...

More Investment Cases

TRACK RECORD

Our Future K&S Commercial production (Phase I)
Doubling production (Phase II)
Garinskoye Production
2016 IRC Tiger Capital shares subscription
K&S Trial production commenced and ramp-up
First iron ore concentrate production
Final hot commissioning and testing
2015 IRC Completed fully underwritten Open Offer
K&S Ongoing commissioning and testing
2014 K&S Commissioning Programme commenced
2013 IRC General Nice + Minmetals Cheerglory Strategic Alliance
K&S Ongoing construction
2012 Kuranakh Ilmenite production full capacity
Garinskoye DSO operation announced
Exploration Ilmenite & Molybdenum
Exploration acquisitions
2011 IRC Group reserves increase threefold
Kuranakh Full year production targets exceeded
K&S First drawdown ICBC facility
Optimisation Study to double K&S production
2010 IRC HKEx listing
Kuranakh Commissioned
Iron ore production full capacity
K&S US$340m ICBC facility
US$400m CNEEC EPC contract
SRP First production